35锤击、静压预应力管桩 作业指导书(2012版)

发布时间:2013-11-03 08:43:47  

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

第 3 部分:变电土建 锤击、静压预应力管桩 作 业 指 导 书 编码:BDTJ-ZW-05

36

锤击、静压预应力管桩作业指导书

目 次

1 适用范围 ························································································································································ 29 2 编写依据 ························································································································································ 29 3 作业流程 ························································································································································ 29 4 工作前安全风险辨析及控制措施 ················································································································ 305 作业准备 ························································································································································ 30 6 作业方法 ························································································································································ 31 7 质量控制措施及检验标准 ···························································································································· 32

37

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

1 适用范围

本作业指导书适用于 110~500kV 电网工程的锤击打预应力管桩工程。

2 编写依据

表 2-1 编 写 依 据

3 作业流程 作业(工序)流程图见图 3-1。

图 3-1 作业(工序)流程图

38

锤击、静压预应力管桩作业指导书

4 安全风险辨析及预控

4.1 锤击、静压预应力管桩作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安 全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。

4.2 按《指南》中与锤击、静压预应力管桩作业相关联的《电网建设安全施工作业票》(编码:BDTJ-ZW-05、 06-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全 员审核,施工负责人签发。

4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员 负责将安全措施落实到各作业任务和步骤中。

4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用 10 天,超过 10 天须重新 办理作业票,在工作完成后上交项目部保存备查。

表 4-1 作业任务安全基准风险指南

5 作业准备 5. 1 人员配备

39

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

表 5-1 人 员 配 备 表

5. 2 主要工器具及仪器仪表配置

表 5-2 主要工器具及仪器仪表配置表

6 作业方法 6. 1 试桩

施工前必须打试验桩,其数量不少于 2 根。确定贯入度并校验打桩设备、施工工艺以及技术措施是 否适宜。

6. 2 桩位放样及控制

6. 2. 1 在打桩现场或附近需设置控制点,数量不少于 2 个;控制点的设置地点应在受打桩作业影响的范 围之外。

6. 2. 2 对施工现场的控制点应经常检查,避免发生误差,根据控制桩对轴线进行放线,然后再定出桩位。 6. 2. 3 桩轴线放线应满足以下要求:双排及以上桩,偏移应小于 20mm;对单排桩,偏移应小于 10mm。 6. 3 桩机就位 桩机就位时,应对准桩位,保证垂直稳定,在施工中不发生倾斜、移动,静压桩机就位

时利用其行 40

锤击、静压预应力管桩作业指导书 走装置完成。

6. 4 吊、插

6. 4. 1 锤击桩。先将桩锤提至超过管桩长度 1m 左右范围内,桩机配备动力将管桩吊起,在桩帽、桩顶 垫上硬纸板做衬垫,即可将桩锤缓慢落到桩顶上面,再将管桩下端的桩尖准确对准桩位,在桩的自重和 锤重的作用下,桩向土中沉入一定深度而达到稳定的位置。

6. 4. 2 静压沉桩。先拴好吊桩用的钢丝绳和索具,利用桩机和自身配置的起重机,将桩管桩吊入夹持器

中夹紧,再调整位置将管桩下端的桩尖准确对准桩位,再启动压桩油缸,把桩管下端 0.3~0.5m 桩身压 入土中。

6. 5 立管校

在桩机正方和侧面各设一个垂球架,控制检查桩机和桩管的垂直度偏差不大于桩长的 0.5%,静压桩 利用液压系统调整桩管至符合施工要求;锤击桩利用桩机撑杆电动机和左右移架调整桩管至符合施工要 求,在第一节桩沉管 2m 范围内,应采用空档或低档锤击桩管,以便于边施工边调整垂直度。

6. 6 沉

6. 6. 1 锤击沉桩。遵守重锤低击的原则,锤重的选择应符合设计要求,桩管分段打入,逐段接长。桩帽 内上下衬垫应符合规定要求,沉桩过程设专人监控、记录。

6. 6. 2 静压沉桩。启动压桩油缸,利用油缸伸程,把桩压入土层中,伸长完后,夹持油缸回程松夹,压

桩油缸回程,如此反复动作,实现连续压桩操作,直至把桩压入。每一次下压,桩入土深度约为 1.5~2.0m, 当一节桩压到其桩顶离地面 80~100cm 时,可进行接桩或放入送桩器将桩压至设计标高。压桩过程设专 人监控、记录。

6. 7 接桩(焊

接)

6. 7. 1 接桩时,其入土部分桩段的桩头宜高出地面 0.5~1.0m,上下节桩段应保持顺直,错位偏差不宜 大于 2mm。

6. 7. 2 管桩对接前,上下端板表面应用铁刷子清刷干净,坡口处应刷至露出金属光泽,焊接时宜先在坡 口圆周上对称点焊 4~6 点,施焊宜由两个焊工对称进行。

6. 7. 3 焊接层数不得少于二层,焊缝应饱满连续,焊好后的桩接头自然冷却 8min 后方可继续锤击。

6. 8 送

6. 8. 1 锤击送桩作业时,送桩器与管桩应相匹配,送桩器与管桩桩头之间应设硬纸板作衬垫,桩锤、桩 帽、送桩器、桩身中心线重合。

6. 8. 2 锤击送桩的最后贯入度参考同一条件的桩不送桩时的最后贯入度予以修

正。

6. 8. 3 静压桩如果桩顶已接近设计标高,而桩压力尚未达到规定值,可以送桩。如果桩顶高出地面一段 距离,而压桩力已达到规定值时则要截桩,以便压桩机移位。

6. 8. 4 静压桩的送桩作业可以利用现场的预制桩段作送桩器。施压预制桩最后一节桩的桩顶面达到施工

地面以上 1.5m 左右时,应再吊一节桩放在被压桩的顶面,不要将接头连接起来。

6. 9 收锤或终止压

41

桩 中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

6. 9. 1 锤击桩收

锤:

1) 桩端位于一般土层时,以控制桩端设计标高为主,贯入度可作参考。

2) 桩端达到坚硬、硬塑的黏性土、中密以上黏土、砂土、碎石类土、风化岩时,以贯入度控制为

主,桩端标高可作参考。

3) 贯入度已达到,但桩底标高未达到时,应继续锤击 3 阵,按每阵 10 击的贯入度不大于设计规定

的数值加以确认,必要时施工控制贯入度应通过试验与有关单位会商确定。

6. 9. 2 静压桩终止压桩控制条

件:

1) 对纯摩擦桩,终压时以设计桩长为控制条件。

2) 对长度大于 21m 的端承摩擦桩,应以设计桩长控制为主,终压力值作对照。

3) 对一些设计承载力较高的桩基,终压力值宜尽量接近桩机满载值。

42

锤击、静压预应力管桩作业指导书

4) 对长 14~21m 静压桩,应以终压力满载值为终压控制条件。

5) 对桩周土质较差且设计承载力较高的,宜复压 1~2 次为佳。

6) 长度小于 14m 的桩,宜连续多次复压,特别对长度小于 8m 的短桩,连续复压的次数应适当增

加。

7 质量控制措施及检验标准

7. 1 质量控制措施

7.1.1 高强混凝土预应力管桩质量控制:运到现场的管桩应按规定要求进行严格检查,对于不合格产品 或次品,坚决退回。

7. 1. 2 桩在运输过程中起吊、堆放必须保持平稳,无大振动,以保证桩身不受损伤。

7. 1. 3 桩位放样:要求设置相对固定的基准点,四角大样与场地地面标高的测定必须准确,基准点一定 要安全保护。

7. 1. 4 桩机就位:桩机就位后必须用经纬仪在桩机两个方向相互垂直的地方,观测桩机、桩的中心线、 设计的桩位是否在同一垂直线上,其偏差不应超过施工规范要求的允许偏差。

7. 1. 5 焊接接桩:焊条性能必须符合设计要求和有关标准的规定,并应有出厂合格证证明。焊接时应在 两侧对称均匀地同时施焊,焊第二道时应将浮渣彻底清除,焊缝质量应符合设计要求。

7. 2 质量控制表

表 7-1 质 量 控 制 表

7. 3 质量检验标准

按照《10kV~500kV 输变电及配电工程质量验收与评定标准 第 3 部分:变电土建工程》中的 Q/CSG 表 3-3.0.18-2、Q/CSG 表 3-5.2.1、Q/CSG 表 3-5.4.15~16、Q/CSG 表 3-BJ2-9、Q/CSG 表 3-BJ2-25~28 规定执行。

43

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

附件 1 安全施工作业票

编码:BDTJ-ZW-05、06-01/01

44

锤击、静压预应力管桩作业指导书

说明:(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。现场负责人开工前核对风险控制措施 并宣读。(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变 更时,应在备注栏记录变更情况。对新增人员进行交底,并签名确认。(三)应根据现场条件、范围和环境,补充安全事 项或平面布置图。(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。(五) 基准风险等级与风险控制措施在开工前现场打“√”。(六)签名不齐全(含代签名的)均作废票处理。

45