第 3 部分:变电土建 建筑屋面作业指导书 编码:BDTJ-ZW-20

146

目 次

1 适用范围 ······················································································································································ 141 2 编写依据 ······················································································································································ 141 3 作业流程 ······················································································································································ 141 4 工作前安全风险辨析及控制措施 ·············································································································· 1425 作业准备 ······················································································································································ 142 6 作业方法 ······················································································································································ 143 7 质量控制措施及检验标准 ·························································································································· 145

147

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

1 适用范围

适用于 110~500kV 电网工程建筑物的屋面隔热、防水施工。

2 编写依据

表 2-1 编 写 依 据

3 作业流程

作业(工序)流程图见图 3-1。

图 3-1 作业(工序)流程图

148

4 安全风险辨析及预控

4.1 建筑屋面作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指 南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。

4.2 按《指南》中与建筑屋面作业相关联的《电网建设安全施工作业票》(编码:BDTJ-ZW-20-01/01), 结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施 工负责人签发。

4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员 负责将安全措施落实到各作业任务和步骤中。

4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用 10 天,超过 10 天须重新 办理作业票,在工作完成后上交项目部保存备查。

表 4-1 作业任务安全基准风险指南

5 作业准备

5. 1 人员配备

表 5- 1 人 员 配 备 表

149

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

5. 2 主要工器具及仪器仪表配置

表 5-2 主要工器具及仪器仪表配置表

6 作业方法 6. 1 屋面找平层

6. 1. 1 屋面找平层施工前应检查结构层和天沟、檐沟的质量及其排水坡度,水落口的标高、管道和预埋 件等的施工质量并验收合格。根据设计的屋面坡度及找平层厚度做好灰饼,并按设计要求做好分格缝(分 格缝不宜大于 6m,采用上宽下窄梯形分格条留缝)。

6. 1. 2 施工前结构层应清理干净,并充分湿润,铺浆前刷素水泥浆一道。铺浆时要压实并严格控制砂浆 配合比,以避免酥松、空壳、起皮。一个分格内砂浆要一次性铺完,不留施工缝。找平层压光不宜少于 三遍,最后一遍抹光应在水泥砂浆终凝前完成。施工完后必须洒水覆盖养护不少于 14d。分格缝内取出 分格条后应清理干净,用油膏嵌满缝。

6. 1. 3 找平层的排水坡度应符合设计要求。平屋面采用结构找坡不应小于 3%,采用材料找坡宜为 2%; 天沟、檐沟纵向找坡不应小于 1%,沟底水落差不得超过 200mm。

6. 1. 4 基层与突出屋面结构(女儿墙、山墙、天窗壁、变形缝、烟囱等)的交接处和基层的转角处,找 平层均应做成圆弧形,圆弧半径应符合表 6-1 的要求。内部排水的水落口周围,找平层应做成略低的 凹坑。

表 6-1 转 角 处 圆 弧 半 径

6. 2 基层处理

150

检查泛水坡度、方向符合设计要求,所有管道、避雷设施安装完毕,并通过验收;所有阴阳角、管 根抹成圆角;做好挑沿、女儿墙、人孔、沉降缝等;沉降缝顶要做坡以利铁皮封盖。施工前应检查、清 理基层,基层处理后经验收合格方可施工。

6. 3 屋面防水

6. 3. 1 卷材(柔性)防水层:防水卷材不得在雨天施工,屋面坡度必须满足排水要求。卷材铺贴前,找 平层应干燥。可用下述方法确定找平层是否干燥:由傍晚至次日晨或在晴天 1~2h 内铺 1m卷材,如卷 材内侧无结露现象,即认为找平层已基本干燥。基层处理剂可采用喷涂或涂刷法施工,喷涂或涂刷应均

匀一致,第二遍应在第一遍干燥的基础上进行,待最后一遍干燥后,方可铺贴卷材,喷涂基层处理剂前, 应用毛刷对屋面节点、周边及拐角等处先行涂刷一遍。

1) 铺贴防水卷材前,应先做好节点,附加层和屋面排水比较集中的部位的处理(屋面与水落口连

接处及檐口、檐沟、天沟、屋面转角、板端缝等),然后由屋面最低标高处向上施工,铺贴天沟、 檐沟卷材时,宜顺着天沟、檐沟的方向,应尽量减少搭接,同时不得污染檐口外侧和墙面。防 水卷材采用胶粘剂粘贴,用热熔或冷粘法贴于基层。

2) 先均匀涂刷基层处理剂,待基层处理剂基本干燥后,顺卷材摊铺方向弹标准线。将卷材摊开,

卷材折叠后面朝上,在屋面基层及卷材背面均匀涂刷胶粘剂,卷材搭接部位不要涂胶,胶粘剂 晾干后,反转卷材沿标准线进行粘贴。铺展卷材时不宜拉得太紧,每铺完一幅卷材,应立即用 压锟沿卷材中间往两端滚压,排除黏结层空气。卷材内不得有空鼓及黏结不牢的现象,卷材搭 接封口处采用专用封口胶封闭。

3) 卷材的搭接方法、宽度及要求,应根据屋面的坡度、最大频率风向、卷材的材性来决定。铺贴

卷材应采用搭接法,卷材应平行屋脊从檐沟处往上铺贴,双向流水坡的卷材搭接应顺水流方向。 长边及端头的搭接宽度均为 80mm,端头接茬要错开,搭接宽度偏差≥10mm。卷材配制应减少 搭接接头,还应尽量避免阴阳角处的接头。铺贴平面与立面相连接的卷材,应由下向上进行, 使卷材紧贴阴阳角。高聚物改性沥青防水卷材和合成高分子防水卷材的搭接缝,宜用材性相容 的密封材料封严。

4) 天沟、檐口处卷材铺贴前,先对水落口进行密封处理,在水落口杯埋设时,水落口杯与竖向插

口的连接处应用密封材料嵌填密实,防止暴雨时产生倒水现象。水落口周围直径 500mm 范围内 用防水涂料或密封材料涂封作为附加增加层,厚度不小于 2mm。由于天沟、檐口部位水流量较 大,在转角处要用密封材料密封,每边宽度不小于 300mm,干燥后增添一层卷材或涂刷涂料作 为附加层。天沟、檐口铺贴卷材应从沟底开始,顺天沟从水落口向分水岭方向铺贴。铺至水落 口的各层卷材和附加增强层均应粘贴在杯口上,用雨水罩的底盘将其压紧,底盘与卷材间满涂 胶结材料。变形缝处附加墙与屋面交接处的泛水部位应增加增强附加层。排气孔与伸出屋面的 管道阴角处两层增强附加层,上部剪开交叉贴实,上端用细铁丝扎牢,用密封材料密封,阴阳 角处用密封材料密封,再铺贴一层卷材附加层。屋面特殊部位的附加增强层和卷材铺贴要求: 檐口位置应将端头的卷材裁齐后压入凹槽内,然后将凹槽用密封材料嵌填密实,如用压条或带 垫片的钉子固定,钉子钉入凹槽内,钉帽及卷材端头压条上下口用密封材料封平。

5) 卷材多层铺贴时接缝应错开,铺贴时随着放卷用喷枪往返均匀加热基层和卷材的交接处,喷枪

距加热面适当,趁卷材的材面刚刚熔化时,将卷材向前滚铺、粘贴,完成后不得出现皱折、空 鼓现象。

6. 3. 2 涂膜(柔性)防水层:基层表面须保持干燥、洁净、不开裂、不起砂。防水涂料应分层分遍涂布,

待先涂的涂层干燥后方可涂布后一遍涂料。涂膜防水层要与基层粘接牢固;涂刷均匀无流淌,不出现露 底、漏涂和堆积现象;收头处理、泛水处理须符合要求。涂膜厚度按设计要求涂刷,最小厚度不小于设 2 151

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

计厚度的 80%。涂膜防水层上的撒布材料应铺撒均匀、粘接牢固。

1) 铺设方向:需铺设胎体增强材料,且屋面坡度小于 15%时,可平行屋脊铺设;屋面坡度大于 15%

时,应垂直屋脊铺设,并由屋面最低处向上铺设。

152

建筑屋面作业指导书

2) 胎体搭接宽度:胎体长边搭接宽度不得少于 50mm,短边搭接宽度不得少于 70mm。

3) 采用二层胎体增强材料时,上下层不得互相垂直铺设,搭接缝应错开,其间距不应少于幅宽的

三分之一。

4) 天沟、檐沟、檐口的泛水等部位,均应加铺有胎体增强材料的附加层;落水口周围与屋面交接

处应做密封处理,并加 铺两层有胎体增 强材料的附 加层,涂膜伸入水落口 的深度不得少于 50mm,防水涂料的收头应用防水材料多遍涂刷或用密封材料封严。

5) 在防水涂料未干前,不得在防水层上进行其他施工作业。

6. 3. 3 隔离层:隔离层应在柔性防水层(或隔热层)表面与细石混凝土防水层间施工,将细石混凝土防 水层与柔性防水层(或隔热层)隔离,可采用纸筋灰、浓石灰水涂刷或空铺卷材隔离。

6. 3. 4 细石混凝土(刚性)防水层:细石混凝土防水层的原材料和配合比必须符合设计要求,并严格控 制混凝土坍落度,浇筑前应采用上宽下窄梯形木条分格,水泥砂浆固定。钢筋网按设计要求绑扎,按分 格缝断开。先薄铺下层混凝土,再将钢筋网提至中上层,后浇筑上层混凝土。细石混凝土防水层与山墙、 女儿墙间设置缝隙,突出屋面的细部构造按设计和规范要求处理。细石混凝土层采用平板振动器振实。 混凝土压光后表面光洁、无抹纹、色泽均匀一致,抹光时不能加水泥浆或干水泥粉。细石混凝土、补偿? 收缩性混凝土和块体刚性防水面层,在施工完成 12~24h 后应及时进行养护。养护时间规定为:对块体 刚性防水不少于 7d,细石混凝土及补偿收缩性混凝土不少于 14d,养护初期屋面不得随便上人。细石混 凝土和补偿收缩性混凝土防水层的分格缝,宜做成上宽下窄,分格条应设在屋面板的支承端、屋面转折 处、防水层与结构的交接处,其纵横宜大于 6m。分格缝内应清理干净,油膏嵌缝应密实。

6. 4 淋(蓄)水试验 淋水试验重点冲淋屋面的细部构造部位及山墙、女儿墙的泛水,注意天沟、水落

口位置是否渗漏。

蓄水试验蓄水应高出屋面最高点 20mm,静置时间不少于 24h,不得有渗漏现象。

6. 5 屋面隔热层 屋面隔热层严禁在雨、雪和五级以上大风和天气施工,施工前要检查保温材料的含水

率是否符合设

计要求,铺设保温隔热层的基层表面应干燥、洁净、平整、无蜂窝、孔洞和裂缝。

6. 5. 1 松散材料隔热层

平面铺设松散的保温材料应分层铺设压实,每层虚铺厚度不宜大于 150mm,其厚度和压实度必须经 过试验确定,压实后不得直接在隔热层上走动或堆放重物。平面铺设时,可每隔 800~1000mm 预埋龙骨 或砌半砖矮隔断,以便控制摊铺厚度及保证屋面坡度。

6. 5. 2 板块隔热层

1) 干铺板块状隔热层:直接铺设在结构层或防水层上,分层铺设时上下两层板块应相互错开,两

块相邻的板边厚度应一致,板间缝隙用同类材料嵌填密实。遇底层凸起时应把板块切断再拼合, 避免两头翘曲。

2) 黏结铺设板块状隔热层:板块状保温材料平粘在层面基层上,铺设前应满涂胶结材料,与基层

之间相互粘牢。一般用水泥混合砂浆黏结,聚苯板材料应用沥青胶结材料。板缝间或缺角处应 用碎屑加胶料拌匀填补严密。

6. 5. 3 整体隔热层

1) 水泥石灰炉渣隔热层施工前用石灰水将炉渣浸透,不得少于 3d,炉渣或水渣应过筛,粒径控制

在 5~40mm,搅拌均匀,一般配合比为水泥:石灰:炉渣为 1:1:8。铺设时分层滚压,按设计 要求控制虚铺厚度和密实度,通过试验确定隔热性能。

2) 沥青膨胀珍珠岩、沥青膨胀蛭石隔热层的材料须搅拌均匀,要求色泽一致,无沥青块,要根据

试验确定压实程度,摊铺厚度应符合设计要求,表面平整。

3) 现喷硬质聚氨酯泡沫隔热层的配合比应符合要求,喷涂时要连续均匀,厚度一致。如基层表面

温度过低时,可先涂一层甲组涂料,再进行喷涂施工。

4) 现浇整体隔热材料应控制好层面坡度和厚度。

153

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

6.5.4 倒置式屋面

1) 设计要求采用倒置式屋面时,其防水层要平整,不得有积水现象。檐口抹灰等工序,应在找平

层施工前完成。倒置式屋面的隔热层应采用吸水率小、长期浸水不腐烂的隔热材料;进行倒置 式屋面冬季施工时,要选用憎水性隔热材料。

2) 采用挤塑聚苯乙烯泡沫塑料做倒置式屋面的隔热层,可用机械方法固定,板缝和固定处的缝隙

应用同类材料碎屑填实,表面应平整。

3) 倒置式屋面的隔热层必须用混凝土、走道板、砾石等保护层,保护层铺设厚度按设计要求,其

与隔热层之间应铺一层隔离层。

6. 5. 5 隔热层排气道 在已铺好的隔热层上进行其他施工作业前必须采取保护措施,保证隔热层不受损;

隔热层容易吸水

且不易挥发,因此施工完成后应及时抹水泥砂浆找平层(或保护层),如含水率过高,应待水分充分挥发 后再施工下一层。隔热层必须设置排气道,排气道宜设置在屋面板的端头接缝处、转角处。排气道宽度 设置为 50~70mm 之间,纵横道应贯通,纵横间距不大于 6m。

另外,也可以将隔热层布置在柔性防水层和细石混凝土(刚性)防水层之间。 7 质量控制措施及检验标准

7. 1 质量控制措施

7. 1. 1 原材料及配合比,必须符合设计要求和屋面工程质量验收规范的规定。

7. 1. 2 找平层施工前应先根据跑水方向、坡度进行打点、冲筋,保证跑水方向正确、坡度均匀;找平前 应浇水湿润,找平层施工中应拉线检查。做到坡度符合要求,平整无积水找平层;施工完工后应及时养 护,避免早期脱水。

7. 1. 3 屋面、天沟、檐沟找平层的坡度,必须符合设计和屋面工程质量验收规范的要求。雨水口、内排 雨口施工过程中,应采取临时措施封口,防止杂物进入堵塞。

7. 1. 4 基层应完全干燥并清理干净后方可进行防水层施工,严禁雨天施工;在施工前应检查管根、地漏 等处是否松动,并及时修补和稳固;在施工中,施工人员应加强对特殊部位处理:平立面交接处、排汽 道口、泛水、变形缝等均应增铺附加层等加强措施。

7. 1. 5 卷材铺贴时应平、实,压边紧密,粘结牢固,防止出现出现空鼓。

7. 1. 6 铺贴卷材时加强细部操作,管根、水落管口、伸缩缝和卷材搭接处,应做好收头黏结,施工中保 护接槎,嵌缝时应清理,使干净的接槎面相粘,以保证施工质量,并认真做蓄水试验。 7. 1. 7 涂膜应根据防水涂料的品种分层分遍涂布,不得一次涂成,涂刷均匀。

7. 1. 8 隔热材料的强度、密度、导热系数和含水率,必须符合设计要求和屋面工程质量验收规范的规定, 严禁有断裂和露筋等缺陷。 7. 2 质量控制表

表 7-1 质 量 控 制 表

154

建筑屋面作业指导书

7. 3 质量检验标准

按照《10kV~500kV 输变电及配电工程质量验收与评定标准 第 3 部分:变电土建工程》中的 Q/CSG表 3-3.0.18-2~3、Q/CSG 表 3-5.2.1、Q/CSG 表 3-5.21.1~11、Q/CSG 表 3-BJ2-1、Q/CSG 表 3-BJ2-6、Q/CSG 表 3-BJ2-9、Q/CSG 表 3-BJ2-60 规定执行。

155

中国南方电网有限责任公司电网建设施工作业指导书 第 3 部分:变电土建

附件 1 安全施工作业票

编码:BDTJ-ZW-20-01/01

156

建筑屋面作业指导书

说明:(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。现场负责人开工前核对风险控制措施 并宣读。(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变 更时,应在备注栏记录变更情况。对新增人员进行交底,并签名确认。(三)应根据现场条件、范围和环境,补充安全事 项或平面布置图。(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。(五) 基准风险等级与风险控制措施在开工前现场打“√”。(六)签名不齐全(含代签名的)均作废票处理。